|
CAPEX PROGRAMME
BACK GROUND:
The recent Business Plan for FY 2008-09 to FY
2012-13 approved by the Hon’ble Commission vide
order dated 20th March 2010 in case
no.41, 42 & 43/ 2007 has envisaged total
investment of `5,000 Cr. by State Govt. through
GRIDCO along with the four DISCOMs under CAPEX
plan for this purpose.
Against this backdrop, GoO has decided to
initiate measures for providing financial
support to the DISCOMs in the form of long term
financial assistance through GRIDCO to meet
substantially the CAPEX requirement of DISCOMs.
The objective is to improve the distribution
system with least impact on tariff and to reduce
AT & C loss for sustainability of the sector.
SCOPE OF THE PROGRAMME:
The focus of the scheme shall be
on system Improvement, establishment of reliable
distribution system, reduction of AT & C loss to
a sustainable level and improvement of quality
of supply to the consumers of the State.
The project coverage includes
renovation/modernization of existing &
installation of new 33/11 KV primary substations
and 11/0.4 KV distribution substations, re-conductoring
of lines at 33 KV and below, load bifurcation,
feeder separation, HVDS (11 KV) lines, aerial
bunched conductoring in theft prone areas,
replacement of electromagnetic energy meters
with tamper proof electronic meters,
installation of capacitor banks, energy audit,
IT system implementation, Mobile service
centers, distribution substation automation with
SCADA system, ring fencing of different project
areas and such other measures for attaining the
above objective.
The following items shall be broadly
included in the scope of this programme:
(i)
Replacement of LT conductors by AB cables
in theft prone areas.
(ii)
Installation of Pillar Box Metering
system.
(iii)
Up-gradation and Replacement of
Transformers (star rated) to cater to additional
load.
(iv)
Up-gradation of 33/11 KV sub-stations.
(v)
Installation/ replacement of Vacuum
Circuit Breakers (VCBs)
(vi)
Replacement of faulty insulators, AB
switches etc. Replacement of existing weak LT/HT
poles.
(vii)
Installation of new 33/11 KV and 11/0.4
KV substations.
(viii)
Re-conductoring in case of old lines with
conductor of optimum size.
(ix)
Conversion of single-phase into 3-phase
system.
(x)
New HT lines both 33 and 11 KV.
(xi)
Extension of HVDS.
(xii)
Installation of Metering Cubicles.
(xiii)
Earthing of Substations.
(xiv)
Installation of lightning Arrestors.
(xv)
Installation of capacitor banks.
(xvi) Installation
of online monitoring and automatic billing
system through AMR.
(xvii)
IT application in distribution
management.
(xviii)
Complete Distribution Transformer
Metering/feeder metering for energy audit
purpose.
(xix)
Provision of boundary wall, fencing &
control room etc. around the Sub-station to
ensure safety of the equipment and human lives
and other such things.
In addition to the above heads of expenses,
consumer metering would be taken up by the CESU
as a composite activity in areas where system
up-gradation is being taken up in order to
reduce loss. This would then form a part of DPR
of the specified area where investment is
proposed.
FUNDING MECHANISM:
The allocation to different DISCOMs will
normally be in the proportion to the number of
consumers of the DISCOMs as on 01.04.2009 (i.e.
CESU 39%, NESCO-21%, WESCO-19.5% & SOUTH
CO-20.5%) as stipulated in the Business Plan
approved by the OERC in their order
dtd.20.03.2010. Year wise beak up of Capex
Programme funding to CESU are as follows:
|
Financial Year |
2010-11
|
2011-12 |
2012-13 |
2013-14 |
Total |
|
State Govt
(out of which) |
117.00 |
156.00 |
97.50 |
97.50 |
468.00 |
|
a. FC Grant @0% |
0.00 |
78.00 |
58.50 |
58.50 |
195.00 |
|
b. SS to FC Grant @0%t |
0.00 |
26.00 |
19.50 |
19.50 |
65.00 |
|
c. Loan to GRIDCO for counterpart funding to
FC Grant @4% |
0.00 |
26.00 |
19.50 |
19.50 |
65.00 |
|
d. State's own contribution@4% |
117.00 |
26.00 |
0.00 |
0.00 |
143.00 |
|
DISCOMs (CESU)
( out of which) |
0.00 |
78.00 |
156.00 |
234.00 |
468.00 |
|
a. Counterpart DISCOMs ( CESU’s) share for
FC Grant |
0.00 |
26.00 |
19.50 |
19.50 |
65.00 |
|
b. DISCOM's ( CESU’s) contribution |
0.00 |
52.00 |
136.50 |
214.50 |
403.00 |
|
Total Capex Funding |
117.00 |
234.00 |
253.50 |
331.50 |
936.00 |
|